OGN News•02-02-2026February 02, 2026•1 min
oil-gasName of Client : Bapco Upstream
Estimated Budget : $500,000,000
Contract Value : $316,000,000
Facility Type : Gas Compression, Non-Associated Gas
Sector : Gas
Main Contractor : Jereh
Location : Awali, Bahrain
Award Date : 2024-Q4
BACKGROUND
BACKGROUND
Bapco Upstream is planning to install seven new non-associated gas compression facilities around the Bahrain field. Collectively the compression stations will have the capacity to process 920 million standard cubic feet per day (MMSCFD).
PROJECT SCOPE
The scope includes installing seven new non-associated gas compression stations.
PROJECT STATUS
As of January 2026, engineering design is nearing completion. The construction work is being conducted by Jereh. The firm will supply some of the main project parts, including the compressors.
PROJECT FINANCE
Bapco Upstream is the client of the project.
PROJECT SCHEDULES
Project Announced: 1Q-2024
EPC ITB: 1Q-2024
EP: 4Q-2024
Completion: 3Q-2027
oil-gas
OGV Energy – News•Apr 3, 2026•2 min
oil-gas
AOG Asian Oil & Gas•Apr 3, 2026•2 min
oil-gas
Pipeline Technology Journal•Apr 3, 2026•2 min
oil-gas
Gas Processing and LNG•Apr 3, 2026•1 min
oil-gas
Gas Processing and LNG•Apr 3, 2026•3 min
oil-gas
Energypedia News•Apr 3, 2026•1 min
oil-gas
Drilling Contractor•Apr 3, 2026•1 min
oil-gas
Tank Storage Magazine – News•Apr 2, 2026•1 min
oil-gas
World Oil•Apr 2, 2026•1 min
oil-gas
World Oil•Apr 2, 2026•2 min
oil-gas
World Oil•Apr 2, 2026•2 min
oil-gas
OGV Energy – News•Apr 2, 2026•2 min
oil-gas
OGV Energy – News•Apr 2, 2026•2 min
oil-gas
Energypedia News•Apr 2, 2026•4 min
oil-gas
Pipeline Technology Journal•Apr 2, 2026•2 min
oil-gas
OGN News•Apr 2, 2026•2 min
oil-gas
OGN News•Apr 2, 2026•5 min
oil-gas
OGN News•Apr 2, 2026•1 min
oil-gas
Offshore Technology•Apr 2, 2026•2 min
oil-gas
Oilfield Technology•Apr 1, 2026•2 min