Update: How Germany Is Building Up Lng Import Terminals

oil-gas
Apr 16, 2025
Article Source LogoGas Processing and LNG
Gas Processing and LNG

Germany has looked to liquefied natural gas (LNG) imports to replace piped Russian gas since Moscow's invasion of Ukraine in 2022.

Its first move has been to deploy floating storage regasification units (FSRUs) to receive seaborne LNG, while longer term it plans shore-based regasification terminals and facilities to import and produce ammonia and green hydrogen.

Below are details of the latest developments:

Mukran. The terminal on Ruegen island in the Baltic Sea supplies onshore grids with LNG via pipeline firm Gascade's new OAL pipeline.

On April 16, private operator Deutsche ReGas reported that there are no more regasification slots available at Mukran for the remainder of 2025, saying LNG carriers are arriving on a weekly basis with around one terawatt hour of gas each.

This comes after ReGas cancelled one of the two FSRUs, the Energos Power, in February, due to low utilization.

It now only employs Norwegian operator Hoegh's FSRU Neptune, having said it struggled with fees offered by state-owned Deutsche Energy Terminal GmbH (DET) to attract cargoes at DET-supervised North Sea terminals.

However, gas demand was set to be strong ahead of next winter, said ReGas, also citing EU decisions to extend requirements to refill underground storage facilities.

Looking long-term, on April 4, ReGas launched a three-month bidding round for expanding Mukran's capacity by offering an additional 5 Bm3y from 2027 to 2043. It wants to restart a second FSRU and restore full capacity of 13.5 Bm3 by 2027.

Lubmin. ReGas and Hoegh in June 2024 signed an agreement to develop the Baltic Sea port, a forerunner of Mukran, into an ammonia/hydrogen import terminal.

Stade. Hanseatic Energy Hub (HEH) in 2024 took a final investment decision for a land-based, ammonia-ready terminal at the Elbe river inland port to start in 2027.

The terminal is expected to cost around €1 B ($1.14 B).

Employment of the FSRU Energos Force, that was expected to run until 2027, ahead of the onshore terminal starting operations, is delayed until further notice after DET and HEH cancelled contracts with each other over unresolved disputes about construction schedules and payments.

Wilhelmshaven. Utility Uniper launched Germany's first FSRU operation, Wilhelmshaven 1, on the North Sea, in 2022.

Uniper plans to add a land-based ammonia import reception terminal and cracker in the second half of this decade to make green hydrogen, and build a 200-MW electrolyser to be fed with local wind power.

DET said there are plans for a second FSRU at Wilhelmshaven but has not specified a commissioning date.

Brunsbuettel. The Brunsbuettel FSRU went into operation in 2023 on the North Sea coast, initially chartered and operated by utility RWE's trading arm before it was handed over to DET.

It is the forerunner of a land-based LNG facility which has been cleared to receive €40 MM of state support.

It could start operations at the end of 2026, when a newly inaugurated, adjacent ammonia terminal could also start up.

($1 = €0.8798)

 

 

Share Your Insights!

Publish your articles, reach a global audience, and make an impact.

4
Recent Comments
JD
JD
John Doe1 week ago
Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius!
100
JD
John Doe1 week ago
Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius!
100
JD
John Doe1 week ago
Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius! Lorem ipsum, dolor sit amet consectetur adipisicing elit. Repudiandae, exercitationem earum hic numquam assumenda voluptatem velit nemo consequatur sed, ullam, iste porro vitae eius placeat dolorum dolore dolor! Inventore, eius!
100

Related News You might want to check out

Exxonmobil To Invest $1.5B In Nigeria’S Deepwater Oil Fields
Energy Capital Power
Exxonmobil To Invest $1.5B In Nigeria’S Deepwater Oil Fields
oil-gas
08 May 2025
Uae Joins Funding For $25 Billion Nigeria-Morocco Gas Pipeline
Pipeline Technology Journal
Uae Joins Funding For $25 Billion Nigeria-Morocco Gas Pipeline
oil-gas
07 May 2025
Federal Jury Sides With Marathon Oil In $123.7 Million Force Majeure Case
World Oil
Federal Jury Sides With Marathon Oil In $123.7 Million Force Majeure Case
oil-gas
07 May 2025
Friedrich Vorwerk Group Wins Contract For New 61Km Section Of South German Gas Pipeline
Pipeline Technology Journal
Friedrich Vorwerk Group Wins Contract For New 61Km Section Of South German Gas Pipeline
oil-gas
06 May 2025
Totalenergies Seeks Permit For $16-B Green Hydrogen Project In Chile
Gas Processing and LNG
Totalenergies Seeks Permit For $16-B Green Hydrogen Project In Chile
oil-gas
06 May 2025
Adnoc Gas Announces Q1 Net Income Of $1.27 Billion, Up 7% Year On Year
World Oil
Adnoc Gas Announces Q1 Net Income Of $1.27 Billion, Up 7% Year On Year
oil-gas
05 May 2025
Sunoco To Acquire Parkland In $9 Billion Deal As Americas Fuel Market Consolidates
Pipeline Gas Journal
Sunoco To Acquire Parkland In $9 Billion Deal As Americas Fuel Market Consolidates
oil-gas
05 May 2025
Sienergy To Acquire Epcor’S Texas Gas Operations, 353 Miles Of Pipeline For $60 Million
Pipeline Gas Journal
Sienergy To Acquire Epcor’S Texas Gas Operations, 353 Miles Of Pipeline For $60 Million
oil-gas
05 May 2025
Bukit Asam Advances $3.1 Billion Coal-To-Synthetic Gas Project In Indonesia
Pipeline Gas Journal
Bukit Asam Advances $3.1 Billion Coal-To-Synthetic Gas Project In Indonesia
oil-gas
05 May 2025
Totalenergies Files For $16 Billion Green Hydrogen, Ammonia Hub In Chile
Pipeline Gas Journal
Totalenergies Files For $16 Billion Green Hydrogen, Ammonia Hub In Chile
oil-gas
05 May 2025
Indonesia'S Bukit Asam Eyes $3.1-B Plant To Convert Coal To Synthetic Natural Gas
Gas Processing and LNG
Indonesia'S Bukit Asam Eyes $3.1-B Plant To Convert Coal To Synthetic Natural Gas
oil-gas
05 May 2025
Spain Unveils Plan For Europe'S Largest Hydrogen Pipeline Network Spanning 2,600 Km
Pipeline Technology Journal
Spain Unveils Plan For Europe'S Largest Hydrogen Pipeline Network Spanning 2,600 Km
oil-gas
30 April 2025
Afreximbank Launches $3B Intra-African Oil Trade Facility
Energy Capital Power
Afreximbank Launches $3B Intra-African Oil Trade Facility
oil-gas
30 April 2025
Indian Oil Inks $1.4 Billion Lng Supply Deal With Trafigura
Pipeline Gas Journal
Indian Oil Inks $1.4 Billion Lng Supply Deal With Trafigura
oil-gas
30 April 2025
Vaquero Midstream To Build 70-Mile Pipeline, Expand Gas Processing Near Waha Hub
Pipeline Gas Journal
Vaquero Midstream To Build 70-Mile Pipeline, Expand Gas Processing Near Waha Hub
oil-gas
29 April 2025
Ukraine’S Naftogaz Secures $466M Financing For Purchasing Gas
Offshore Technology
Ukraine’S Naftogaz Secures $466M Financing For Purchasing Gas
oil-gas
29 April 2025
The Liaohe Gas Storage Group Injected More Than 20 Billion Cubic Meters Of Gas
Gulf Oil and Gas
The Liaohe Gas Storage Group Injected More Than 20 Billion Cubic Meters Of Gas
oil-gas
29 April 2025
Spain’S 1,615-Mile Hydrogen Network Advances Ahead Of Schedule, Enagas Says
Pipeline Gas Journal
Spain’S 1,615-Mile Hydrogen Network Advances Ahead Of Schedule, Enagas Says
oil-gas
28 April 2025
Oman To Build 400Km Hydrogen Pipeline Network
Arabian Gulf Business Insight
Oman To Build 400Km Hydrogen Pipeline Network
oil-gas
28 April 2025
Liaohe Oilfield: Refreshing Concepts And Gathering Strength To "Return To 10 Million Tons"
Gulf Oil and Gas
Liaohe Oilfield: Refreshing Concepts And Gathering Strength To "Return To 10 Million Tons"
oil-gas
28 April 2025