Advertise your business here! 🚀

Contact us now and get more customers.

Smiling woman thumbs up

Hs2 Project Team Reveals Challenges Of 4-Day Continuous Viaduct Slide Over Road And Railway

road-bridge
Feb 03, 2025
Article Source LogoNew Civil Engineer (Bridge)
New Civil Engineer (Bridge)

The High Speed 2 (HS2) project team behind the construction of the Small Dean viaduct have revealed the challenges behind sliding the 4,500t, 345m long structure over a road and a railway in one continuous stage over four days.

Constructing the viaduct marks the heaviest and longest single stage viaduct deck slide of the whole HS2 project so far, culminating four years of work that has involved preparing the site, diverting utilities and realigning the road.

The four day operation was completed yesterday, 2 February, and involved sliding the deck across the A413 and Chilterns Railways line near Wendover in Buckinghamshire in one go.

This viaduct, as well as nearby Wendover dean viaduct, have innovative “double composite” structures, with layers of reinforced concrete on top and bottom of the steel structure. The side of the Small Dean beam also features prominent deck stiffeners which help to manage the structural forces while allowing for a more structurally efficient span.

The viaduct is being delivered by HS2’s main works contractor, EKFB, made up of Eiffage, Kier, Ferrovial Construction and Bam Nuttall, working with their design partner, ASC (a joint venture between Arcadis Setec and Cowi).

An aerial view of the viaduct in its final position

Speaking on site in the midst of the four-day slide, EKFB senior project manager Martin Gamble told NCE: “It’s the only HS2 viaduct that has a road and a railway involved and believe me that has been a challenge at times over the last few years.

“The complexity of the interfaces with the road and railway have provided a real challenge which, with the assistance of Network Rail and Buckinghamshire Council, we have risen to and overcome.”

The viaduct’s concrete and steel deck was assembled to its full 345m length before the slide began. Most of the precast concrete deck slabs were also installed in advance of the launch. These decisions increased the weight of the slide but allowed the team to save time during the later stages of the project.

HS2 Ltd project manager Jason Bicknell told NCE that “we tend to have to launch viaducts over three or four stages, this one we were able to do it all in one go”.

One reason for the team deciding to do the slide continuously concerned the topography, according to Bicknell. Having a large and long embankment allowed them to build the whole viaduct before beginning to move it.

“The second reason we’ve done it this way is because it means we only have to close the A413 for one day, which reduces disruption to locals,” he added.

He further explained that, while doing it in one operation presented challenges, the situation also provided an opportunity.

“This is a really unique situation, it was a big challenge at the design stage to come up with something that would allow is to cross and dissect the railway all at the same time,” he said.

“We’ve worked continuously throughout the whole thing next to the railway [in preparation], building the six piers we’ve got between the two large abutments and they are piled quite deep; they’re about 45m deep piles.”

Small Dean Viaduct deck in position above the railway, February 2025

One of the hardest elements of construction the viaduct involved the lifting of the structure’s hammerhead piers to hold the deck.

EKFB agent Elliot Bright explained that they “are made offsite and brought in before we lift them in. They’re 45t, which is quite heavy, we’re able to install one in about half an hour.

“[After lifting the piers into position], the next bit is lifting in the prefabricated reinforcement cage. This is probably the most difficult element we had with the piers because you have to fit them inside where there’s only 30/40mm gap all the way around.

“They don’t fit very well, so you have to get them in and wobble it around, look into the cage and see where the conflicts are.

“The first one took us about eight hours to do but the last one took about an hour and a half so we got a bit better by the end.”

The nose of Small Dean viaduct deck over the A413

With the deck now in position, engineers can begin the challenging job of lowering it by 600mm onto the permanent bearings, which will support the full weight of the viaduct. The two-month long operation will see it carefully lowered by 200mm at a time, pier-by pier, until the whole deck settles into its final position.

The viaduct is one of only two places in the Chilterns where the HS2 route will be above ground level, with the underside of the viaduct just 6m above the road, supported by the huge Y-shaped piers.

The piers to support the viaduct deck were completed in April last year.

The video below includes a timelapse of the Small Dean viaduct deck slide operation.

Like what you've read? To receive New Civil Engineer's daily and weekly newsletters click here.

Share Your Insights!

Publish your articles, reach a global audience, and make an impact.

0
Recent Comments

Road and Bridge Related News You might want to check out

View by
Italy To Reclassify 3.6Km £11Bn Sicily Bridge As Defence Spending To Meet Nato Objectives
Italy To Reclassify 3.6Km £11Bn Sicily Bridge As Defence Spending To Meet Nato Objectives
New Civil Engineer (Bridge)
01 July 2025
road-bridge
Hs2 Completes Three-Day Slide Of 220M-Long Viaduct Deck In Northamptonshire
Hs2 Completes Three-Day Slide Of 220M-Long Viaduct Deck In Northamptonshire
New Civil Engineer (Bridge)
24 June 2025
road-bridge
Adept Welcomes Government’S £1 Billion Investment In Vital Road Structures
Adept Welcomes Government’S £1 Billion Investment In Vital Road Structures
Highway News
18 June 2025
road-bridge
Centre Halts Goa Ring Road Project Until 40-Km Highway Work Finishes
Centre Halts Goa Ring Road Project Until 40-Km Highway Work Finishes
Construction World
12 June 2025
road-bridge
Delhi To Build 5-Km Tunnel Linking Shiv Murti And Mandela Road
Delhi To Build 5-Km Tunnel Linking Shiv Murti And Mandela Road
Construction World
12 June 2025
road-bridge
Walsh Construction To Replace Decrepit Providence Bridge For $339M
Walsh Construction To Replace Decrepit Providence Bridge For $339M
Global Construction Review-Road
11 June 2025
road-bridge
Rhode Island’S Washington Bridge Replacement To Cost $571 Million
Rhode Island’S Washington Bridge Replacement To Cost $571 Million
Roads & Bridges
09 June 2025
road-bridge
Balfour’S £208M Lincolnshire Road Job Heads To Inquiry
Balfour’S £208M Lincolnshire Road Job Heads To Inquiry
Construction News
09 June 2025
road-bridge
Spain’S $108M A-127 Regional Road Upgrade Guaranteed By Assured Guaranty
Spain’S $108M A-127 Regional Road Upgrade Guaranteed By Assured Guaranty
Highways Today - Road
08 June 2025
road-bridge
£225M Carlisle Southern Link Road Construction Makes Advances Amid Dry Spring
£225M Carlisle Southern Link Road Construction Makes Advances Amid Dry Spring
New Civil Engineer (Road)
06 June 2025
road-bridge
$964 Million Road Maintenance Blitz Now Complete
$964 Million Road Maintenance Blitz Now Complete
Roads & Infrastructure
06 June 2025
road-bridge
£115M Melton Mowbray Distributor Road Construction Entering Final Phase
£115M Melton Mowbray Distributor Road Construction Entering Final Phase
New Civil Engineer (Road)
04 June 2025
road-bridge