Petition Of Cerc (Connectivity And General Network Access To The Inter-State Transmission System) Regulations Of The Land Required From The Date Of Grant Of Final Connectivity – Eq

ByArticle Source LogoEQ Mazagine04-16-20263 min
EQ Mazagine
powerplant

Summary:

##  Key Business Prayers by SUCRL

| Prayer | Description ||——–|————-|| **Prayer (a)** | Allow land document submission within 12 months of final connectivity / coordinates, not 18 months from in-principle grant. || **Prayer (b)** | Alternative: 18–24 months before scheduled start date (31 Dec 2029). || **Prayer (c)** | Alternative: Reallocate connectivity to another Bikaner substation with finalized location & 2027 start date. || **Prayer (d)** | Release Land BG & Conn BG 2 & 3; retain only 5% of Land BG (₹2 crore) + Conn BG1 as nominal security. |

##  CERC Analysis & Key Legal/Business Findings

### Issue 1 – Timeline for Land Documents

– **3rd Amendment to GNA Regulations (effective 9 Sept 2025)** introduced a **proviso to Regulation 11A(1)**:If final connectivity is granted **without coordinates**, the developer gets **9 months from communication of tentative coordinates** to submit land documents.– CERC’s own **Order dated 8 Dec 2025 in Petition 14/SM/2025** clarified:> Even if final connectivity is delayed by CTUIL, developers must get **at least 9 months** from coordinate communication.

**Decision on Issue 1:**– The deadline of **26 Jan 2026 is set aside**.– SUCRL will get **at least 9 months from communication of coordinates** by CTUIL.– Request for **12 months** (instead of 9) – **not granted at this stage**.– Request for reallocation to another substation – **not directed**; SUCRL may apply under **Regulation 11C** (transfer/reallocation provisions).

### Issue 2 – Bank Guarantees (Land BG & Conn BGs)

SUCRL argued:– Delay is solely CTUIL’s fault.– Under **Regulation 3.7.3**, if an applicant *withdraws* before final connectivity, forfeiture is only:– 100% application fee– 5% of Land BG– Encash Conn BG1– Return Conn BG2 & BG3 (if no ATS awarded)

**Decision on Issue 2 – Unique Business Relief Granted:**

> CERC invoked **Regulation 42 (Power to Remove Difficulty)** and allowed:

1. **Option to withdraw** connectivity application within **3 months** of this order.2. If withdrawn:– Full Land BG (₹40 cr) + all Conn BGs returned within 15 days.– Forfeiture: only **50% of application fee** (not 100%).– Balance 50% fee returned.3. If SUCRL **chooses to continue**:– All BGs remain with CTUIL as per regulations.

##  General Direction to CTUIL (Impact on Other Developers)

CERC noted CTUIL’s submission that **~60 GW of connectivity applications** face similar issues (Bikaner-V, Barmer-III, Bhadla-IV, etc.) due to transmission planning challenges (lack of load centers, need for HVDC, etc.).

**CERC directed CTUIL to:**– Within **30 days**, give a **similar withdrawal option** to **all such applicants**.– If withdrawn:– Full return of Land BG & Conn BGs– Forfeiture of only **50% application fee**– Give wide publicity to this order.

##  Final Disposition

– **Petition No. 666/MP/2025** and all IAs (**54/2025, 118/2025, 119/2025, 132/2025**) are **disposed of**.– SUCRL gets a **clear, time-bound withdrawal option** with **minimal forfeiture**.– If SUCRL continues, the original BG regime applies, but land document timeline is **extended via the 9-month rule** from coordinate communication.

For more information please see below link: