Reportedly, Alpex Solar’s board has approved the upgrade of its proposed solar cell facility in Kosi Kotwan, Uttar Pradesh, from 1.6 GW to 2.2 GW and transition to advanced G12R tunnel oxide passivated contact (TOPCon) technology.
The capex for the transition and expansion is estimated at Rs 31.36 billion, to be funded entirely through internal accruals. The first will establish 1.4 GW of G12R TOPCon capacity with trial production targeted for the first quarter of 2026–27. The second phase will add 800 MW within six months of phase I completion, with the full 2.2 GW facility expected to be operational during 2026–27.