Data Center Executives Pivot Toward Onsite Power, Per New Report

powerplant
Jan 22, 2025
Article Source LogoPOWER Engineering
POWER Engineering

Onsite turbines, reciprocating engines and fuel cells will increasingly power data centers, according to a survey by fuel cell manufacturer Bloom Energy.

In April and November 2024, Bloom surveyed a range of managers to C-suite executives from hyperscaler and colocation developer companies. The 100 data center leaders make decisions about power systems architecture.

Historically, data centers have used onsite power mostly for backup purposes. The shift toward onsite power generation as a primary source of power comes in response to data centers facing grid connection delays. Leveraging onsite power could also ease pressure on the nation’s aging electric grid.

In November, data center leaders said they expected approximately 30% of all data center sites to use some onsite power as a primary energy source supplemental to the grid by 2030, 2.3 times more than just seven months earlier.

The report noted there were more data center announcements featuring onsite power in 2024 than the previous four years combined.

“We were surprised by the pace of change and the growing expectation that onsite power generation will play a greater role in powering data center projects,” reads the Bloom Energy report.

Data center leaders also expect power availability to get worse.

In the U.S., 55 GW of data center IT capacity is expected to come online in the next five years, according to the report. An additional 35 GW of data center capacity is expected to be announced during that time.

Data centers, while not the only reason for load growth in the U.S., are the largest driver. Data centers by 2030 could require 8-12% of the total U.S. demand, compared to 3-4% today, according to the report.

As new data center projects struggle to get timely access to power, data center leaders are seeing value differently. Time to power is playing an increasingly important role in this equation.

Save the date for DTECH Data Centers and AI from May 27-29, 2025 in San Jose, CA! This new event brings utilities, data center operators and other stakeholders together to discuss the strategies necessary to navigate power constraints, project delays, and the increasing demand for sustainable, flexible solutions.

Bloom Energy predicts that their decisions will go beyond traditional factors, like reliability and cost.

The company’s report found that leaders are now ready to invest 50% more than seven months ago if that means they can access power faster for upcoming data center projects.

“This shift underscores an important insight: being online ahead of competitors is a strategic advantage, particularly for AI data centers,” reads the report. “Leaders recognize that accelerating power access is key to securing a leading position in this rapidly evolving landscape.”

Combined-cycle gas turbines (CCGT) are primarily being used in large AI training data centers that require 500 MW or more capacity. Smaller inferencing data centers – focused on the application of trained models – are more often relying on simple cycle turbines, sometimes paired with batteries.

While these turbine technologies are currently the most common onsite power solutions, long supply chain lead times and higher carbon dioxide emissions are limiting factors in their adoption.

Fuel cells, which convert natural gas or hydrogen into electricity, are gaining popularity in data center projects because they are quick to deploy and produce fewer emissions and less pollution than natural gas-fired turbines.

While fuel cells can be more expensive than some other solutions, the Bloom Energy report noted that data center leaders often prioritize them for their faster deployment, easier permitting and greater power density.

In November, we reported that AEP agreed to secure up to 1 gigawatt (GW) of Bloom Energy solid oxide fuel cells for data centers and other large energy users who need to quickly power their operations while the grid is still being built out to accommodate demand.

Data center leaders are also optimistic about emerging technologies such as geothermal power, small modular reactors (SMRs) and gas generation with carbon capture and sequestration (CCS).

Bloom Energy is seeing these technologies appear in data center companies’ long-term roadmaps. The company said recent announcements related to these technologies focus on data centers that are expected to go online after 2030, due to the technologies’ early stage of development.

Share Your Insights!

Publish your articles, reach a global audience, and make an impact.

0
Recent Comments

Power Plant Related News You might want to check out

View by
Global Solar Tracker Shipments Reach 111 Gw In 2024
Global Solar Tracker Shipments Reach 111 Gw In 2024
PV Magazine
13 June 2025
powerplant
Solarium Green Energy To Restart Solar Module Production With New 1 Gw Plant
Solarium Green Energy To Restart Solar Module Production With New 1 Gw Plant
PV Magazine
12 June 2025
powerplant
India Prepares Solar Waste Policy As Installations Top 100 Gw And Disposal Challenge Looms – Eq
India Prepares Solar Waste Policy As Installations Top 100 Gw And Disposal Challenge Looms – Eq
EQ Mazagine
12 June 2025
powerplant
Duke Energy Advances New 1.4-Gw Gas-Hydrogen Power Plant In South Carolina Under New Energy Security Mandate
Duke Energy Advances New 1.4-Gw Gas-Hydrogen Power Plant In South Carolina Under New Energy Security Mandate
Power News
11 June 2025
powerplant
Water-Based Photovoltaics Reach Global Capacity Of 21.18 Gw
Water-Based Photovoltaics Reach Global Capacity Of 21.18 Gw
PV Magazine
11 June 2025
powerplant
Plug Power And Aga Expand Partnership With 2 Gw Electrolyser Deal In Uzbekistan
Plug Power And Aga Expand Partnership With 2 Gw Electrolyser Deal In Uzbekistan
Renewable Watch
11 June 2025
powerplant
Us Solar Developers Secure Over $1 Billion For 1.4 Gw Of Projects
Us Solar Developers Secure Over $1 Billion For 1.4 Gw Of Projects
PV Magazine
11 June 2025
powerplant
India Offers $631.5 Million To Support 30 Gwh Of Battery Storage
India Offers $631.5 Million To Support 30 Gwh Of Battery Storage
PV Magazine
11 June 2025
powerplant
India Successfully Met Peak Power Demand Of 241 Gw On 9Th June, 2025 With Zero Peak Shortage: Shri Manohar Lal – Eq
India Successfully Met Peak Power Demand Of 241 Gw On 9Th June, 2025 With Zero Peak Shortage: Shri Manohar Lal – Eq
EQ Mazagine
11 June 2025
powerplant
Saatvik Solar To Develop 4 Gw Module Manufacturing Facility In Odisha
Saatvik Solar To Develop 4 Gw Module Manufacturing Facility In Odisha
Renewable Watch
10 June 2025
powerplant
Purvah Green Power Signs 1 Gw Wtg And O&M Agreement With Envision Energy
Purvah Green Power Signs 1 Gw Wtg And O&M Agreement With Envision Energy
Powerline
10 June 2025
powerplant
Tata Power Hits 4 Gw Of Solar Module Production Capacity
Tata Power Hits 4 Gw Of Solar Module Production Capacity
PV Magazine
10 June 2025
powerplant